County Road 2 (Broadway Avenue)
Planned Construction Phases
The reconstruction of Broadway Avenue will take two construction seasons to complete. The 2011 construction season will soon be behind us as the contractor completes miscellaneous tasks and cleans up the site for winter. All roadways will be open to traffic during winter suspension. A minimum of one lane of traffic will be maintained in both directions along Broadway Avenue throughout construction in 2012. The following graphics illustrate the remaining stages to be completed in 2012.
The legend below applies to all of the following construction stages.
|
2012 Construction: Stage 5 (May-June)

Planned Construction :
- Public utility work
- Construct north side of Broadway Avenue (7th Street to Centennial Dr.)
Traffic:
- 4th Street Closed – Follow detour
- Traffic shifted to south side of Broadway Avenue
|
|
2012 Construction: Stage 6 (July-August)

Planned Construction :
- Public utility work
- Construct south side of Broadway Avenue (7th Street to Centennial Dr.)
Traffic:
- Traffic shifted to north side of Broadway Avenue
|
|
2012 Construction: Stage 7 (September-October)

Planned Construction :
- Complete remaining surface work and clean up
|
|
2011 Completed Construction on Background Page
2011 Completed Construction on Background Page
|
|
Mn/DOT Construction
Find details on other road construction
in the area of Forest Lake.
|
|
Lake Street & Broadway Ave. Roundabout
Learn more about Roundabouts at
Roundabout U! On the Roundabout U site you will find a link to the Forest Lake Roundabout brochure, which provides a step-by-step guide
to navigating the Forest Lake Roundabout.
|